Which of the following is not one of the six categories of


1. Which of the following is not one of the six categories of cost presented in the textbook?

Price of Goods

Variable Manufacturing Costs

Fixed Manufacturing Costs

Semi Variable Costs

Total Production Costs

2. Which of the following statements about critical path scheduling is not true?

The critical path is the longest path through the network

Critical path scheduling allows managers to not manage non-critical activities

As a manager, we need to know the critical path to identify which activities we should focus our efforts on controlling

A delay in a critical path activity delays the expected project completion time

Critical path analysis lets us know which activities do not need to be managed as strictly.