Which of the following is a true statement about


1. Identify the document that is developed from the project scope statement, the project work breakdown structure (WBS) and the WBS dictionary that will be part of the procurement documents package.

A. Contract Management Plan.

B. Make-or-Buy Analysis.

C. Organizational Process Assets.

D. Statement of Work.

2. Which of the following is a true statement about Procurement Documents?

A. Procurement Documents should be structured to facilitate accurate and complete responses from prospective sellers.

B. Procurement Documents are used to solicit responses from prospective sellers.

C. Procurement Documents should include a copy of the buyer's contract.

D. All of the above.

3. Which of the following is a true statement concerning evaluation criteria found in an RFP?

A. They can often be found in a Procurement Document.

B. They can be objective or subjective.

C. They may be limited to price if the product, service, or result is readily available from a significant number of sellers.

D. None of the above

E. All of the above.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Which of the following is a true statement about
Reference No:- TGS01508806

Expected delivery within 24 Hours