Which machine is the bottle-neck


Problem

A group of five workstations produces a product. Answer the following questions using the input, output, and capability per hour data in the chart below.

a) Calculate the number of units waiting at Workstations 2, 3, 4, and 5 after eight hours. Explain your answers.

b) Which machine is the bottle-neck? Explain your answer.

1

2

3

4

5

Input

60

60

40

40

38

Capability

60

40

60

38

60

Output

60

40

40

38

38