Which dispatching rule has the best score for flow time


Problem:

The following jobs are waiting to be processed at Rick Carlson's machine center. Carlson's machine center has a relatively long backlog and sets fresh schedules every 2 weeks, which do not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers.

Job Date Job Received Production Days Needed Date Job Due

BR-02 228 15 300

CX-01 225 25 270

DE-06 230 35 320

RG-05 235 40 360

SY-11 231 30 310

Required:

Question 1) Complete the table. (Show your supporting calculations)

Question 2) Which dispatching rule has the best score for flow time?

Question 3) Which dispatching rule has the best score for utilization metric?

Question 4) Which dispatching rule has the best score for lateness?

Question 5) Which dispatching rule would you select? Support your decision.

Solve the given numerical problem and illustrate step by step calculation.