Which control chart should be used for the above data and


Answer the given question of Total Quality Management.

A manufacturing plant make wind mill assemblies & can produce 50 units in a month in two period of 15 days each ; following is the data for number of defects arising per month.

Month                                

Jan

Feb

Mar

Apr

MAy

Jun

July

Aug

Sept

Oct

Nov

Dec

No. of defects per period

4

3

1

4

6

7

9

5

2

0

2

4

 

3

2

0

5

7

7

6

4

3

2

3

3

• which control chart should be used for the above data and why?

• Make the appropriate control chart on a graph paper.

• interpret the chart and give your recommendation. Whether the process is in control or not?