Which batches should machine center b be used


In a job shop Machine Center A has a ten minute set-up time per batch and a two minute per unit run time. Machine Center B performs the identical function but has a set-up time of thirty minutes and a one minute run time per unit. The job shop makes products in batches ranging from one unit to one hundred units. Assuming capacity is not a limitation on either machine, on which batches should Machine Center B be used?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Which batches should machine center b be used
Reference No:- TGS080191

Expected delivery within 24 Hours