Which activities to shorten to cut project by four weeks


A construction project is broken down into the following 10 activities:

Activity Immediate Predecessor Time (Weeks)
1 -- 4
2 1 2
3 1 4
4 1 3
5 2, 3 5
6 3 6
7 4 2
8 5 3
9 6, 7 5
10 8, 9 7

a. Draw the network diagram

b. Find the critical path.

c. If activities 1 and 10 can't be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost $10,000 per week, which activities would you shorten to cut the project by four weeks?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Which activities to shorten to cut project by four weeks
Reference No:- TGS084491

Expected delivery within 24 Hours