Which activities should be crashed to meet a project


Please see the case in attachment.

Here is the questions, Remaining responses for schedule compression should use the question-response format.

Schedule Compression:

What is the crash cost per day for each activity?

Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? You may assume that you can partially crash an activity.

What is the new cost after crashing the project?

Fully crash the project to its minimum duration. Prepare a table that shows (for each day the project length is reduced) the project duration, the activities that are crashed, the incremental crash cost, and the total crash cost.