Which activities should be crashed to meet a project


Given the following:

Activity

Crash Time (days)

Crashed Cost (total)

Normal Time (days)

Normal Cost

A: Obtain Instructor

4

$800

7

$500

B: Locate a Room

2

350

3

200

C: Check Costs

4

900

6

500

D: Room Open?

1

500

3

200

E: Schedule Class

1

550

2

300

1. Find the crash cost per day

2. Which activities should be crashed to meet a project deadline of 10 days with a minimum cost?  Assume partial crashing is allowed.

3. Find the new cost

4. Is partial crashing an appropriate assumption in this kind of project?

Solution Preview :

Prepared by a verified Expert
Project Management: Which activities should be crashed to meet a project
Reference No:- TGS02285658

Now Priced at $20 (50% Discount)

Recommended (96%)

Rated (4.8/5)