Where are the main opportunities to improve the cycle time


The following data consists of the actual time used and potential (the best time possible for this review process)to complete each step in the review process. The actual times are based on the review of 30 projects. The potential times are subjective engineering judgment estimates.

Table: Basic Data Review for Construction Project Equipment Arrangement

 

 

 

Cycle Time (hours)

 

Step

Description

Actual

Potential

Difference

1

Read basic data package

4

4

-

2

Write, type, proof, sign, copy, and distribute cover letter

21.9

0.5

21.4

3

Queue

40

0

40

4

Lead engineer calls key people to schedule meeting

4

0.25

3.75

5

Write, type, proof, sign, copy, and distribute confirmation letter

25.4

2.1

23.3

6

Hold meeting; develop path forward and concerns

4

4

-

7

Project leader and specialist develop missing information

12

12

-

8

Determine plant preferred vendors

12

12

-

9

Review notes from meeting

12

12

-

10

Resolve open issues

106

104

2

11

Write, type, proof, sign, copy, and distribute basic data acceptance letter

26.5

0.25

26.25

 

Totals

267.8

151.1

116.7

Use the data in thetable above and answer the following questions in the space provided below:

1. What are the sources of value-added and non-value-added work in this process?

2. Where are the main opportunities to improve the cycle time of this process, with respect to both actual time used and the potential best times? What strategy would you use?

3. Step 10:Resolve Open Issues required 104 hours (potential) versus 106 hours (actual). Is there an OFI here? Why or why not? If so, how would you attack it?

4. What do you think are the most difficult critical issues to deal with when designing a sound cycle time study such as this one?

Solution Preview :

Prepared by a verified Expert
Basic Statistics: Where are the main opportunities to improve the cycle time
Reference No:- TGS01212879

Now Priced at $40 (50% Discount)

Recommended (97%)

Rated (4.9/5)

A

Anonymous user

3/2/2016 1:58:09 AM

By using the data of the table illustrated in the assignment regarding construction project and equipment arrangement; respond to the following questions: 1) Determine the resources of value-added and non-value-added work in this procedure? 2) Where are the major opportunities to enhance the cycle time of this procedure, with respect to both actual time employed and the potential best times? What approach would you employ? 3) Resolve Open Issues required 104 hours (potential) vs. 106 hours (actual). Is there an OFI here? Explain why or why not? If so, how would you attack it? 4) What do you believe are the most difficult vital issues to deal with whenever designing a sound cycle time study for instance this one?