When the resource levelling feature is activated


Assignment task: When the resource levelling feature is activated, how does Project automatically resolve resource overallocation? Question options:

a) Project delays or splits resource work, thus delaying start times. The project finish date may or may not pushed back. b)Custom options regarding resource levelling are entered by the user.

c) Project delays or splits resource work, thus delaying start times. The project finish date is pushed back.

d) Project increases the costs associated with the overallocated resources and the schedule remains unchanged.

Request for Solution File

Ask an Expert for Answer!!
Other Management: When the resource levelling feature is activated
Reference No:- TGS03326237

Expected delivery within 24 Hours