When shotcrete lagging is used the upper portion of the


When shotcrete lagging is used, the upper portion of the shoring system (equivalent to the depth to which the piles will be removed) will be wood lagging. In relation to the shotcrete lagging installation, when should the formwork in front of the wood lagging be installed?

Request for Solution File

Ask an Expert for Answer!!
Civil Engineering: When shotcrete lagging is used the upper portion of the
Reference No:- TGS01535597

Expected delivery within 24 Hours