When an activity has two precedent activities its early


When an activity has two precedent activities, its early start time is equal to:

a) The later of the two precedent activities’ “Early Start” times

b) The activity’s start time minus its duration

c) The earlier of the two precedent activities’ “Early Finish” times

d) The later of the two precedent activities’ “Early Finish” times