What would be the unit cost of labor for the next 350 units


Instead of an 80% learning curve, the supplier believes that a 90% learning curve will be more indicative of what will occur in the future (starting at unit 51). What would be the unit cost of labor for the next 350 units using a 90% learning curve? Show calculations that use the formulas that are provided in the posted learning curve articles.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What would be the unit cost of labor for the next 350 units
Reference No:- TGS02941015

Expected delivery within 24 Hours