What would be the change in thecompany


A corporation is trying to determine how long ittakes for one product to pass through the production process. Thefollowing information was gathered regarding how many days theproduct spent in various production activites:

Activity Number of days

Inspection..........................................5

Storage..............................................6

Assemby............................................3

Handling.............................................2

Painting..............................................3

Packing...............................................1

C. Determine the company's manufacturingeffeciency ratio.

D. If the company implements a total qualitymanagemnet program and a just-in-time system, which of the aboveactivities could be eliminated? What would be the change in thecompany's manufacturing effeciency ratio?