Consider the following table resulting from lot sizing by the Wagner Whitin algorithm:

Month

Demand

Min. Cost

Order Period

1

69

85

1

2

29

114

1

3

36

186

1

4

61

277

3

5

61

348

4

6

26

400

4

7

34

469

5

8

67

555

8

9

45

600

8

10

67

710

10

11

79

789

10

12

56

864

11

(a) Develop the optimal ordering schedule with the relative quantities.

(b) What will the schedule be if your planning horizon was only six months?