What will be the average time for the 20 missile guidance


United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The first unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 3,200 hours and cost $21,000 in materials and equipment usage. Labor cost is charged at $18 per hour.

The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls.

a. What will the last unit cost to build?

b. What will be the average time for the 20 missile guidance controls?

c. What will the average cost be for guidance control for the 20 in the contract?

Solution Preview :

Prepared by a verified Expert
Operation Management: What will be the average time for the 20 missile guidance
Reference No:- TGS0659931

Now Priced at $30 (50% Discount)

Recommended (99%)

Rated (4.3/5)