What was x companys total overhead flexible budget variance


Problem

At the beginning of the year, X Company expected to produce 3,400 units of its only product. Its estimate of fixed overhead was $11,000, and its estimate of variable overhead per unit was $7.00.

At the end of the year, 2,800 units were actually produced, with actual total overhead cost of $29,528.

What was X Company's total overhead flexible budget variance for the year [a positive number means a favorable variance; a negative number means an unfavorable variance]?