What was the total cost including the costs of raw


Use the following to answer questions:

Groats Catering uses activity-based costing for its overhead costs. The company has provided the following data concerning the activity rates in its activity-based costing system:

 

Activity Cost Pools

Preparing Meals

Arranging Functions

 

Wages.......................

$1.15

$180.00

 

Supplies.....................

$0.40

$320.00

 

Other expenses..........

$0.15

$130.00

The number of meals served is the measure of activity for the Preparing Meals activity cost pool. The number of functions catered is used as the activity measure for the Arranging Functions activity cost pool.

Management would like to know whether the company made any money on a recent function at which 150 meals were served. The company catered the function for a fixed price of $18.00 per meal. The cost of the raw ingredients for the meals was $12.40 per meal. This cost is in addition to the costs of wages, supplies, and other expenses detailed above.

For the purposes of preparing action analyses, management has assigned ease of adjustment codes to the costs as follows: wages are classified as a Yellow cost; supplies and raw ingredients as a Green cost; and other expenses as a Red cost.

1. According to the activity-based costing system, what was the total cost (including the costs of raw ingredients) of the function mentioned above? (Round to the nearest whole dollar.)

A) $2,945

B) $2,745

C) $2,095

D) $2,245

2.  Suppose an action analysis report is prepared for the function mentioned above. What would be the "red margin" in the action analysis report? (Round to the nearest whole dollar.)

A) $(45)

B) $(195)

C) $(145)

D) $105

2.  Suppose an action analysis report is prepared for the function mentioned above. What would be the "yellow margin" in the action analysis report? (Round to the nearest whole dollar.)

A) $183

B) $288

C) $233

D) $108

Request for Solution File

Ask an Expert for Answer!!
Database Management System: What was the total cost including the costs of raw
Reference No:- TGS0899930

Expected delivery within 24 Hours