What was the standard rate per-machine hour if the standard


Question - The managerial accountant at Aquatics Pools and Spas assess a fixed overhead budget variance of $3,400 U in the month of April. The standard hours in April were 2,900 hours and the standard rate was projected at $13 per machine-hour. There were unforeseen complications that involved raw materials and the standard rate projected per machine hour - was inaccurate. What was the standard rate per-machine hour if the standard fixed overhead cost of production is $41,100? What is the budgeted fixed overhead amount if the actual fixed overhead is $43,100?

A) $12.15/machine hour; $40,200

B) $14.15/machine hour; $46,500

C) $14.17/machine hour; $39,700

D) $13.86/machine hour; $44,500

Solution Preview :

Prepared by a verified Expert
Accounting Basics: What was the standard rate per-machine hour if the standard
Reference No:- TGS02385437

Now Priced at $20 (50% Discount)

Recommended (95%)

Rated (4.7/5)