What was the predetermined overhead rate


Kansas Company uses a standard cost accounting system. In 2014, the company produced 28,200 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $12.00. Normal capacity was 50,450 direct labor hours. During the year, 130,200 pounds of raw materials were purchased at $0.90 per pound. All materials purchased were used during the year.

If total budgeted manufacturing overhead was $332,970 at normal capacity, what was the predetermined overhead rate? (Round answer to 2 decimal places, e.g. 2.75.) Predetermined overhead rate $