What was the actual hourly wage rate


Health Construction builds standard prefabricated wooden frames for walls. Each frame requires 10 direct labot hours and the standard hourly direct labor rate is $ 18. During July, the company produced 670 frames and worked 6,800 direct labor hours. Payroll records indicate that workers earned $ 127, 500.

a. What were the standard hours for July construction?

b. Calculate the direct labor variances.