What should record the cost of the land and new building


On January 15, 2013, Talbot Corporation purchased a parcel of land as a factory site for $425,000. An old building on the property was demolished, and construction began on a new building which was completed on November 31, 2013. Salvaged materials resulting from the demolition were sold for $12,000. Costs incurred during this period included: Demolition of old building, $35,000, Architect's fees, $15,000, Legal fees for title investigation and purchase contract, $7,000, and Construction costs, $980,000. what should record the cost of the land and new building ?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What should record the cost of the land and new building
Reference No:- TGS042491

Expected delivery within 24 Hours