What sequence should orders be filled


Manny Company produces three products, X, Y, and Z, with the following characteristics:

X Y Z

Selling price per unit $20 100% $16 100% $15 100%

Variable cost per unit 12 60 12 75 6 40

Contribution margin per unit $ 8 40% $ 4 25% $ 9 60%

Machine hours per unit 5 hours 3 hours 6 hours

The company has only 2,000 machine hours available each month. If demand exceeds the company's capacity, in what sequence should orders be filled if the company wants to maximize its total contribution margin? You must show work to support your answer.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What sequence should orders be filled
Reference No:- TGS0555393

Expected delivery within 24 Hours