What is the variable overhead rate variance what is the


The measure of activity in the standard costing system used at ROC, SRL is fabrication hours. The company's flexible manufacturing overhead budget and then data regarding the most recent period's operations are given below:

Flexible Budget:

Budgeted Level of Activity: 5,300 fabrication hoursOverhead costs at the Budgeted activity level:
Variable Overhead Cost: $19,027
Fixed Overhead Cost: $29,521Most Recent period's operations:
Actual level of activity: 5,000 fabrication hours
Standard level of activity for output: 4,800 fabrication hours
Actual total variable overhead cost: $17,700
Actual total fixed overhead cost: $27,150

PART A- What is the variable overhead rate variance?
PART B- What is the variable overhead efficiency variance?
PART C- What is the fixed overhead budget variance?
PART D- What is the fixed overhead volume variance?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: What is the variable overhead rate variance what is the
Reference No:- TGS02549482

Now Priced at $10 (50% Discount)

Recommended (90%)

Rated (4.3/5)