Uxmaiz Corporation had only one job in process during May-Job X32Z-and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below:
|
|
| Beginning balance |
$ |
5000 |
| Charged to the job during May |
|
|
| Direct materials |
$ |
8,000 |
| Direct labor |
$ |
2,000 |
| Manufacturing overhead applied |
$ |
4,000 |
| Units completed |
|
100 |
| Units in process at the end of May |
|
0 |
| Units sold during May |
|
40 |
|
|
In May, overhead was overapplied by $300. The company adjusts its cost of goods sold every month for the amount of the overhead that was underapplied or overapplied.
|
| Required: |
|
1. Using the indirect method, determine the cost of goods sold for May?
|
2. What is the total value of the finished goods inventory at the end of May?
| 3. |
What is the total value of the work in process inventory at the end of May? |
|
|