A manufacturer of solid state drives (SSDs) has projected the next six months of demand to be as shown the table below:

Supply/Demand Info

Beginning

Jan

Feb

Mar

Apr

May

Jun

Forecast (demand)

 

56,600

55,400

62,600

52,400

45,800

52,200

Regular production

 

 

 

 

 

 

 

Overtime production

 

 

 

 

 

 

 

Subcontract production       

 

 

 

 

 

 

 

Ending inventory

4,400

 

 

 

 

 

 

Hired employees

 

 

 

 

 

 

 

Fired employees

 

 

 

 

 

 

 

Total employees

190

 

 

 

 

 

 

Cost variables are as follows:

Cost Variables       


Labor cost/hour

$19

Overtime cost/unit

$32

Subcontracting cost/unit   

$24

Holding cost/unit/month   

$14

Hiring cost/employee

$2,600

Firing cost/employee

$5,100

Here is some additional relevant (capacity) information:

Capacity Information       


Total labor hours/SSD

4

Regular production units/employee/month   

200

Max regular production/month

57,800

Max overtime production/month

5,000

Max subcontractor production/month

4,600

Assuming the company ONLY uses overtime and/or subcontract production if regular production capacity is not sufficient, answer the following questions:

A. What is the regular production cost (over the six months from January through June) for a CHASE production plan?

B. What is the total overtime production cost for this production plan?

C. What is the total subcontract cost for this production plan?

D. What is the total holding cost for this production plan?

E. What is the total hire cost for this production plan?

F. What is the total fire cost for this production plan?

G. What is the total cost (sum of all costs) for this production plan?