Computing Job Costs (LO - 4-3) Weaver Company's predetermined overhead rate is $18.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-200. 

Direct Materials ...... $200 
Direct Labor .......... $120 

Required:

1. What is the total manufacturing cost assigned to Job a-200?

2. If Job A-200 consists of 50 units, what is the average cost assigned to each unit included in the job?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: What is the total manufacturing cost assigned to job a-200