What is the total labor cost variance for job


Job #35 was budgeted to require 3.5 hours of labor at $11.00 per hour. However, it was completed in 3 hours by a person who worked for $14.00 per hour. What is the total labor cost variance for Job #35?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What is the total labor cost variance for job
Reference No:- TGS0718311

Expected delivery within 24 Hours