What is the total cost of job upon completion


Juanita corporation uses a job-order cost system and applies overhead on the basis of direct labour cost. At the end of october, Juanita had one job still in process. The job cost sheet for this job contained the following info:

direct materials $560
Direct labout $170
Manufacturing overhead applied $510

An additional $90 of labour was needed in november to complete this job. What is the total cost of this job upon completion?

a)$1330

b)$260

c)$1240

d)1600