What is the total cost of job no. 1


Moran Company uses a job order cost system and has established a predetermined overhead application rate for the current year of 150% of direct labor cost, based on budgeted overhead of $900,000 and budgeted direct labor cost of $600,000. Job no. 1 was charged with direct materials of $36,000 and with overhead of $27,000. What is the total cost of job no. 1?