What is the total cost associated with lot-sizing technique


An item has a setup cost of $100 and a weekly holding cost of $0.50 per unit. Given the following net requirements, what should the lot sizes be using lot-for-lot (L4L), economic order quantity (EQQ) and least total cost (LTC)? Also, what is the total cost associated with each lot-sizing technique?

Period (in weeks) 1 2 3 4 5 6 7 8 Total
Gross Requirement 10 30 10 50 20 40 50 30

Request for Solution File

Ask an Expert for Answer!!
Business Management: What is the total cost associated with lot-sizing technique
Reference No:- TGS0108341

Expected delivery within 24 Hours