What is the tools-n-time''s total material variance


Tools-N-Time has a standard of 1.5 pounds of materials per unit, at $4 per pound. In producing 2,000 units, Tools-N-Time used 3,100 pounds of materials at a total cost of $12,090.

what is the Tools-N-Time's total material variance ?

 