What is the time estimate of an activity in which the


What is the time estimate of an activity in which the optimistic estimate is 2 days, pessimistic is 12 days, and most likely is 4 days? Show your work. What is the time estimate of an activity in which the optimistic time is 5 days the likely time is 8 days, and the pessimistic time is 14 days? Show your work