What is the throughput manufacturing cycle time for the


Hart Manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 54% of the total throughput (manufacturing cycle) time is spent on non-value-added activities. Delivery cycle time is 18.00 hours, waiting time during the production process is 5.00 hours, queue time prior to starting the production process is 4 hours, and inspection time is 1.8 hours. What is the throughput (manufacturing cycle) time for the operation? (Round your answer to 2 decimal places.) 18.00 hours correct 13.00 hours 6.17 hours 14.00 hour

Solution Preview :

Prepared by a verified Expert
Business Management: What is the throughput manufacturing cycle time for the
Reference No:- TGS02861672

Now Priced at $10 (50% Discount)

Recommended (90%)