What is the throughput manufacturing cycle time


The management of Granger Sports Equipment has been maintaining delivery performance data in order to improve the co's cust. service. Data for the most recent month follows: Manufacturing Cycle Efficiency(MCE) 30.8% Wait time to the start of production 5.0 days, Delivery Cycle time 18 days, Move time 3.0 days, Inspection time 2.5 days, Queue Time during the production process 3.5 days.

What is the Throughput Manufacturing Cycle time?

 