What is the throughput manufacturing cycle


Hart Manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 45% of the total throughput (manufacturing cycle) time is spend on non-value-added activities. Delivery cycle time is 12 hrs, waiting time during the production process is 3 hrs and queue time prior to starting the production process is 2 hrs and the inspection time is 1.2 hrs. What is the throughput (manufacturing cycle) time for the operation?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What is the throughput manufacturing cycle
Reference No:- TGS0719115

Expected delivery within 24 Hours