What is the takt time what are the minimum number of


Takt time question:

Task     Time

A           45 min.

B            50 min.

C            40 min.

D            55 min.

E             40 min.

F             65 min.

G             25 min.

H             35 min.

For this exercise, don't worry about task predecessors.

The working day is seven hours.

The required output is 360 units per day (per seven hour working day).

What is the takt time?

What are the minimum number of workstations needed?

What is the idle time?

What is the percent idle time?

What is the efficiency delay?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the takt time what are the minimum number of
Reference No:- TGS02226497

Expected delivery within 24 Hours