You have been charged with developing a time standard for a certain task. In a preliminary study, you timed one worker perform the task 13 times with an average observed time of 17 seconds and a standard deviation of 3.7 seconds.

What is the standard time for this task if the employee worked at a 17.4 slower pace than average, and an allowance of 30.1 percent of job time is used?