What is the slack or float for activity c show your


The following data were obtained from an in-house MIS project:

Activity Duration Predecessors

Activity Duration Predecessors 

A        3 Days   ---          

B        6 Days   ---          

C        3 Days   B            

D        2 Days   A            

E        3 Days   C,D          

F        2 Days   A            

G        4 Days   F            

H        7 Days   B

I        2 Days   C,D

J        4 Days   H,I

K        8 Days   H,I

L        5 Days   E,G,J

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity E? Show your calculations.

f) What is the slack or float for Activity J? Show your calculations.

Problem 2.

A project to remodel an office area has the following activities.

Activity

Duration

Predecessors

A

3 months

---

B

2 months

---

C

3 months

---

D

4 months

A, B

E

3 months

A

F

2 months

B, C

G

2 months

F

H

1 month

G

I

4 months

D, E, F

J

5 months

H

a) What are the critical path activities? (5 points)

b) What is the project's scheduled completion time? (5 points)

c) What is the slack or float for Activity B? Show your calculations. (1 point)

d) What is the slack or float for Activity D? Show your calculations. (1 point)

e) What is the slack or float for Activity F? Show your calculations. (1 point)

f) What is the slack or float for Activity I? Show your calculations. (1 point)

Problem 3

Information from a room addition project:

 

 

Duration

Predecessors

 

A

2 wks

 

 

B

3 wks

 

 

C

5 wks

 

 

D

7 wks

   A

 

E

3 wks

    B

 

F

2 wks

    C

 

G

4 wks

     F

 

H

1 wk

      A

 

I

8 wks

    D, E, G

 

J

5 wks

             F

 

K

2 wks

  D, E, G, H

 

 

 

 

 

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity A? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations

e) What is the slack or float for Activity H? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations

Problem 4

InformAtion from a site renovation project:

Task     Duration            Predecessors

A          2 wks               _

B          5 WKS             A

C          3 WKS             B

D          15 WKS           B

E          8 WKS             C

F          10 WKS           C

G         2 WKS             D

H          6 WKS             E, F, G

I           5 WKS             H

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity I? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations.

Solution Preview :

Prepared by a verified Expert
Other Subject: What is the slack or float for activity c show your
Reference No:- TGS01035840

Now Priced at $28 (50% Discount)

Recommended (98%)

Rated (4.3/5)