What is the schedule variance at the end of period 5-nbsp


Given the following information for the latest period (5), answer the questions below:

· Actual costs to date are $550.
· The original budget through period 5 was $350.
· The revised costs for the project at completion (EAC) are $9,000.
· The sum of the earned values to date is $400.
· The total original budget (BAC) for the project was $7,000.
· The reserve/contingency fund has not been used.

a. What is the schedule variance at the end of period 5?

b. What is the cost variance at the end of period 5?

c. Given the current information, will the project finish on schedule and on budget? Justify your answer.

Request for Solution File

Ask an Expert for Answer!!
Management Information Sys: What is the schedule variance at the end of period 5-nbsp
Reference No:- TGS01558194

Expected delivery within 24 Hours