What is the schedule performance index what is the estimate


Joe, the project manager of Highlander, Inc., has been executing a project. On July 30, 2013 the project was 60% complete and he needs help with the following measurements:

Activity

Completion Date

PV ($M)

EV ($M)

AC ($M)

A

January 30, 2013

8

8

13

B

February 28, 2013

4

3

6

C

March 30, 2013

6

8

4

D

April 30, 2013

15

12

10

E

May 30, 2013

20

20

25

F

June 30, 2013

9

8

4

G

July 30, 2013

20

14

21

H

August 30, 2013

15

0

0

I

September 30, 2013

25

0

0

a. What is the cost variance?

b. What is the schedule variance?

c. What is the cost performance index?

d. What is the schedule performance index?

e. What is the estimate at completion?

f.  What is the estimate to complete?

g. What is the variance at completion?

h. What is the resource utilization efficiency?

i. What is the resource utilization index?

j. What is the percent complete?

k. What is the percent spent?

l. What is the status of the project?

Respond to questions a-l. You should have a total of 12 answers

2. Describe the planning-monitoring-controlling cycle. In your response make sure you discuss the importance of designing the monitoring system, collecting the data, and the verbal measures.

Your response should be at least 500 words in length. You are required to use at least your textbook as source material for your response. All sources used, including the textbook, must be referenced; paraphrased and quoted material must have accompanying citations.

3. The control system should be well-balanced. Identify four factors for creating a well-balanced control system and explain how they contribute to a well-balanced control system.

Your response should be at least 500 words in length. You are required to use at least your textbook as source material for your response. All sources used, including the textbook, must be referenced; paraphrased and quoted material must have accompanying citations.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the schedule performance index what is the estimate
Reference No:- TGS0998525

Expected delivery within 24 Hours