What is the projects irr accept or reject the project again


Assume the following for a project under evaluation:

** The project's life is 4 years.

** The total time zero, initial cost of $55,000.

** The total net operating cash flow each year is $15,000.

** In addition to the terminal year operating cash flow, there is a non-operating, terminal year cash flow of $8,000.

What is the project's IRR? Accept or reject the project? Again, assume the cost of capital for a project of this risk is 7%.

7%; indifferent to accept or reject

8.4%; reject

8.4%; accept

15.75%, reject

15.75%: accept