Question: Project K costs $52,125, its expected net cash inflows are $12,000 per year for 8 years, and its WACC is 12%.

a) What's the project's NPV?

b) What's the project's IRR?

c) What's the project's MIRR?

d) What's the project's payback?

e) What's the project's discounted payback?