What is the process time


Waltner Corporation's management reports that its average delivery cycle time is 20.0 days, its average throughput time is 13.5 days, its manufacturing cycle efficiency (MCE) is 0.44, its average move time is 0.2 day, and its average queue time is 4.0 days.

Required:
a.

What is the wait time? (Round your answer to 1 decimal place.)

  Wait time   days
b.

What is the process time? (Round your answer to 2 decimal places.)

  Process time   days
c.

What is the inspection time? (Round your answer to 2 decimal places.)

  Inspection time   days

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What is the process time
Reference No:- TGS0673365

Expected delivery within 24 Hours