1. Using the below information, calculate the schedule durations for a 68.26%, 95.44% and 99.73% confidence level? Optimistic = 58 days Most likely = 65 days Pessimistic = 77 days

2. What is the PERT late outcome assumptions and how does the graph differ from a normal distribution bell curve?