What is the npv for a project whose cost of capital is 15


What is the NPV for a project whose cost of capital is 15 percent and initial after-tax cost is $5,000,000 and is expected to provide after-tax operating cash inflows of $1,800,000 in year 1, $1,900,000 in year 2, $1,700,000 in year 3, and $1,300,000 in year 4?

-$1,700,000

-$371,764

-$137,053

-$4,862,947

Solution Preview :

Prepared by a verified Expert
Accounting Basics: What is the npv for a project whose cost of capital is 15
Reference No:- TGS01358431

Now Priced at $6 (50% Discount)

Recommended (99%)

Rated (4.3/5)