What is the normal time-standard time


Question: Peter Rourke, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. The allowances for tasks such as tis are personal. 7%; fatigue, 10%; and delay, 3%.

TASK                     PERFORMANCE                       OBSERVATIONS (MINUTES)

ELEMENT                   RATING (%)                  1            2           3            4             5

 

1                                    110                         5             4           6            4             4

2                                      95                         6             8           7            6             7

3                                      90                          6            4           7            5             5

4                                      85                         1.5          1.8        2.0          1.7         1.5


Q1. What is the normal time?

Q2. What is the standard time?

Solution Preview :