What is the normal time-standard time


Problem: Peter Rourke, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. The allowances for tasks such as tis are personal. 7%; fatigue, 10%; and delay, 3%.

TASK              PERFORMANCE              OBSERVATIONS (MINUTES)

ELEMENT           RATING (%)              1         2         3         4          5

1                           110                      5         4         6         4          4

2                            95                       6         8         7         6          7

3                            90                       6         4          7         5          5

4                             85                     1.5      1.8       2.0      1.7       1.5

Q1. What is the normal time?

Q2. What is the standard time?

Solution Preview :