What is the normal time for each work element


Problem: A job, consisting of four elements, was randomly observed five times for a time study. The following table shows the results (figures are in seconds):

Work Elements Observations    Performance Rating
1. Prepare patty    40    41    50    48    36    0.8
2. Cook first side    78    81    77    89    83    1.1
3. Flip, press, cook the other side 54    55    59    58    63    1.3
4. Assemble    28    24    27    26    32    0.9

Q1. What is the Normal Time (in seconds) for each work element?

Q2. What is the Standard Time (in seconds) for the job if there is a 20% of the job time allowance for personal needs and unavoidable work delays?

Solution Preview :

Prepared by a verified Expert
Other Management: What is the normal time for each work element
Reference No:- TGS01858815